| Meeting RuWatSIP June 10th 2014 | A meeting attended by Director Qader, Sen. Hydrogeologists in MRRD, Norplan (Abrar, Banks, De Jong, Eqar) and more agreed on the following:
Documentation by Dave on agreed action for exploratory drilling, incl. agreed action Report format for use for Environmental Impact Assessment (EIA) before drilling. Very important that MRRD mobilize fast if the work is going to be completed in 2014. |
| Exploratory wells locations and design. ( see doc by Dave) | ![]() |
![]() |
Field work MRRD and DACAAR teams |
|
|||
![]() |
![]() |
![]() |
||
Information and photos from water supply development for Maymane which has stopped A water supply project was started but not completed. 3 well were drilled. |
||||
![]() |
![]() |
![]() |
||
| Preparation 10/11/13 |
| Important background documents | David Banks prepared the following guidelines: The above reports provide the background and the main surveying, sampling and monitoring to be cone in connection with the exploratory drilling and subsequent test-pumping.
|
![]() |
|
| Results - logs | Results - logs from first well: ( more photos) - Time Log Drilling log from first well, ( 107 m deep) |
![]() |
![]() |
||
Progress 28th Oct.14 |
Report from Eng Hadi(DACAAR) with a little bit more explanation from Prof.Eqrar |
|
![]() |
||
| Click above to see the details of the well log. Borehole depth of 120 m | Drill Cuttings from the well at 90 meters depth. | |
![]() |
![]() |
|
| Flow meter procured | New stop valves added. | |
| See more photos | ||
![]() |
|